# Banatie Project Roadmap ## ๐ŸŽฏ Current Status **Phase:** Pre-launch / ICP Validation **Date:** October 30, 2025 **Version:** 1.0 **Next Milestone:** Complete ICP validation by Nov 3, 2025 --- ## ๐Ÿš€ Active Sprint (Oct 20 - Nov 3) ### โœ… COMPLETED - [x] Market positioning clarified (converge AI gen + CDN, not pure AI image generation) - [x] ICP hypothesis validated internally (founder IS the ICP - AI-powered developers) - [x] Pricing strategy drafted (hybrid credits + subscription model) - [x] MVP scope defined (MCP + core features, 4-6 week timeline) - [x] Documentation framework established (filesystem MCP approach) ### ๐Ÿ”„ IN PROGRESS - [ ] **ICP External Validation** (DUE: Nov 3, 2025) Owner: Oleg Status: 0 / 10 interviews completed Blocker: Need to post on Reddit/Indie Hackers **Action items:** - [ ] Create throwaway Reddit account (stealth mode) - [ ] Post in r/ClaudeAI: "How do you handle images in Claude Code?" - [ ] Post in r/ChatGPTCoding: "AI-assisted devs: image generation workflow?" - [ ] Conduct 10-15 text-based interviews via DM - [ ] Fill validation scorecard after each interview - [ ] Make GO/PIVOT/STOP decision based on results ### โธ๏ธ BLOCKED / WAITING - [ ] MVP development (blocked by ICP validation - need confirmed feature priorities) - [ ] Beta user outreach (blocked by validation - need validated messaging) - [ ] Pricing finalization (pending ICP confirmation of willingness to pay) --- ## ๐Ÿ“… Upcoming Milestones ### Week 1-2 (Nov 4-17): POST-VALIDATION **IF GO decision (60%+ willing to use, 40%+ willing to pay $20+):** - [ ] Finalize MVP scope based on validated top 3 needs from interviews - [ ] Begin MCP server development (Week 1: Core generation pipeline) - [ ] Prepare beta access list from interviews (early adopters identified) - [ ] Plan soft launch strategy (Reddit post schedule, messaging) **IF PIVOT decision (<60% interest OR weak willingness to pay):** - [ ] Select alternative ICP (agencies? e-commerce? different dev segment?) - [ ] Prepare new interview script tailored to alternative ICP - [ ] Run 5-10 more interviews (deadline: 1-2 weeks) - [ ] Final GO/STOP decision with hard deadline **IF STOP decision (<40% interest, no one willing to pay):** - [ ] Document learnings (what didn't work, what insights gained) - [ ] Thank all interviewees professionally - [ ] Decide: tackle different problem OR shut down project - [ ] Focus energy back on day job (reduce stress, reassess in 3-6 months) --- ### Week 3-8 (Nov 18 - Jan 5, 2026): MVP DEVELOPMENT *(Assuming GO decision)* **Development timeline (4-6 weeks):** - **Week 3-4:** Core generation pipeline + MCP integration - REST API endpoints finalized - Prompt Enhancement Agent working - Image generation with @name references - Basic storage + CDN integration - **Deliverable:** Working API (generate + upload + references) - **Week 5:** MCP implementation - MCP server setup (follow spec) - Implement 3 tools: banatie_generate, banatie_upload, banatie_list_images - Test with Claude Desktop - Documentation for MCP usage - **Deliverable:** Working MCP integration - **Week 6:** Transformations + UI refinement - Image transformation service (Imageflow or Cloudflare) - Refine demo UI (code snippets, transformation previews) - Dashboard (history, usage stats) - API key management - **Deliverable:** Functional UI for testing - **Week 7:** Payments + polish - Stripe integration (credit packs: $20, $50, $100) - Free tier limits enforcement (10/month with watermark) - Landing page copy + design - API documentation (REST + MCP) - **Deliverable:** Monetization-ready product - **Week 8:** Beta testing + iteration - Invite 5-10 validated users from research - High-touch onboarding (help with MCP setup) - Gather feedback, fix critical bugs - Iterate on UX pain points - **Deliverable:** Product-market fit signals or pivot triggers --- ### Month 4-6 (Jan-Mar 2026): SOFT LAUNCH & GROWTH **Month 4 (Jan):** First paying customers - Goal: 5-10 beta users onboarded - 50+ generations completed - 2+ users purchase credits (willingness to pay validated) - Target MRR: $200-500 **Month 5 (Feb):** Soft launch to communities - Post in r/ClaudeAI: "Show HN: Generate images from Claude Code via MCP" - Indie Hackers build-in-public post - Dev.to technical content (tutorial: "Automate image gen in Next.js with Claude Code") - Target MRR: $500-1,000 **Month 6 (Mar):** Growth optimization - SEO content (start ranking for "AI image generation API", "Claude Code images") - Community building (Discord, Reddit presence) - Case studies from early users - Target MRR: $1-2K (Side Project Validation milestone) --- ## ๐ŸŽฏ Long-term Goals (6-12 months) ### Month 6: Side Project Validation Checkpoint **Success criteria:** - MRR: $1-2K - Customers: 10-20 paying - Churn: <5% monthly - Signal: Product-market fit OR clear pivot needed **Decision:** Continue scaling OR reassess viability --- ### Month 9: Hybrid Mode Decision **Success criteria:** - MRR: $3-5K - Customers: 30-50 paying - Usage: Predictable growth pattern **Options:** - Negotiate 4-day work week with employer (80% salary = $4.8K) - OR: Stay full-time job, continue nights/weekends - Combined income: $7-10K/month (meets family needs + buffer) --- ### Month 12: Full-time Leap Evaluation **Success criteria:** - MRR: $6K+ (current salary replacement) - OR: 12-month runway saved + high confidence in growth - OR: MRR = $4-5K + spouse (Ekaterina) involved in admin with income **Decision:** Go full-time on Banatie OR continue hybrid **Long-term vision (24-36 months):** - $15-30K MRR: Sustainable solo/small team business - Hire 1-2 people (support, marketing, or tech) - Consider Ekaterina full-time on admin/ops --- ## ๐Ÿšฆ Decision Gates ### GATE 1: ICP Validation (Current - Nov 3, 2025) **Success criteria (ALL must be met):** - 60%+ interviews say "I would use this" (6 out of 10) - 40%+ willing to pay $20+ (4 out of 10) - 30%+ want early access (3 out of 10) - Consistent pain point validated (not scattered) - Budget confirmed (they pay for other tools) **Possible outcomes:** - โœ… **GO** โ†’ Build MVP for AI developers (strong signals) - ๐Ÿ”„ **PIVOT** โ†’ Test different ICP (weak signals, 1-2 more weeks) - ๐Ÿ›‘ **STOP** โ†’ Shut down or fundamental rethink (no market fit) **Review meeting:** Nov 4, 2025 with @men --- ### GATE 2: MVP Launch Readiness (Week 8 - Late Dec 2025) **Success criteria:** - MCP integration works reliably (95%+ success rate) - 5-10 beta users onboarded and generating images - 50+ generations completed (usage validated) - 2+ users purchase credits (monetization validated) - No critical bugs blocking core workflow **Possible outcomes:** - โœ… **LAUNCH** โ†’ Soft launch to r/ClaudeAI, Indie Hackers - ๐Ÿ”„ **ITERATE** โ†’ 1-2 more weeks bug fixes, UX improvements - ๐Ÿ›‘ **PIVOT** โ†’ Different approach needed (MCP too complex? Different features?) **Review meeting:** Late December 2025 --- ### GATE 3: PMF Validation (Month 6 - March 2026) **Success criteria:** - $1-2K MRR achieved - <5% monthly churn (customers staying) - "Can't live without" feedback from 3+ users - Organic word-of-mouth starting (referrals, shares) - Usage growing without marketing spend **Possible outcomes:** - โœ… **SCALE** โ†’ Invest in growth (content, partnerships, paid ads eventually) - ๐Ÿ”„ **OPTIMIZE** โ†’ Refine product, improve conversion - ๐Ÿ›‘ **PIVOT/STOP** โ†’ No PMF achieved after 6 months, reassess fundamentally **Review meeting:** April 2026 --- ## โš ๏ธ Risk Mitigation Watch ### HIGH PRIORITY RISKS **1. Burnout Risk (Severity: HIGH)** - **Factors:** Full-time job + side project + newborn (Kirill, 2 weeks old) + family of 5 - **Current exposure:** Working 60+ hrs/week total (40 job + 20 Banatie) - **Monitor:** Weekly health check-ins (Sundays) - **Mitigation:** - Strict time boundaries (no work after 10 PM) - One full day off per week (family only) - Use Agent Coding (Claude Code) to maximize efficiency - Cut scope ruthlessly (MVP, not full vision) - **Red flags:** Physical health decline, family tension, day job performance suffering - **Abort criteria:** If health/family at risk, pause Banatie (not worth it) --- **2. Financial Pressure Risk (Severity: HIGH)** - **Factors:** Zero savings buffer, school tuition coming, single income ($6K/month) - **Current exposure:** No emergency fund, Daniel's private school pending - **Monitor:** Monthly expense tracking, runway calculation - **Mitigation:** - Keep day job until Banatie โ‰ฅ $6K MRR (non-negotiable) - Negotiate hybrid work arrangement early (6-month mark if traction) - Bootstrap (no fundraising until PMF clear) - Minimize Banatie expenses (use family VPS, free tools) - **Red flags:** Credit card debt accumulating, school tuition unpaid, family stress over money - **Abort criteria:** If Banatie costs exceed $500/month without revenue --- **3. No PMF Risk (Severity: HIGHEST)** - **Factors:** Unvalidated ICP, new category (convergence play), complex product - **Current exposure:** Hypothesis not yet tested with external users - **Monitor:** Interview feedback, churn rate, usage metrics, qualitative signals - **Mitigation:** - Brutal ICP validation BEFORE building more (current sprint) - Launch ultra-MVP (not full platform) - 10-15 customer interviews BEFORE launch - Set clear pivot triggers (see Phase 1 decision point) - **Red flags:** No one willing to pay, high churn (>10%), "cool idea, but..." feedback - **Abort criteria:** After 6 months, if <$500 MRR and no PMF signals โ†’ shut down --- **4. Employer Discovery Risk (Severity: MEDIUM)** - **Factors:** Building side project while employed, same industry (web dev, AI) - **Current exposure:** Public presence needed for marketing (Twitter, LinkedIn, dev.to) - **Monitor:** LinkedIn/social mentions, colleague conversations - **Mitigation strategies:** (see `backlog/06-future-topics-backlog.md` - "ัะฒะตั‡ะตะฝะธะต ั„ะตะนัะฐ") - Use separate brand identity (Banatie, not personal) - Delay LinkedIn posting until closer to launch - Focus on dev.to, Indie Hackers (less employer monitoring) - Check employment contract for IP clauses - **Red flags:** Employer asks about side projects, colleagues mention seeing Banatie - **Abort criteria:** If employer explicitly forbids, negotiate exit OR pause publicly --- ## ๐Ÿ“Š Key Metrics Dashboard **Updated:** Weekly (every Sunday evening) ### Validation Metrics (Current Sprint - Oct 20 - Nov 3) - Interviews completed: **0 / 10** - Positive responses ("I would use"): **- / -** - Willing to pay $20+: **- / -** - Early access requests: **- / -** ### Development Metrics (After validation - Nov+) - MVP features completed: **- / 8** - Beta users onboarded: **- / 10** - Generations completed: **- / 50** - Credit purchases: **- / 2** ### Business Metrics (Post-launch - Jan+) - **MRR:** $0 - **Paying customers:** 0 - **Churn rate:** N/A - **Conversion rate (Free โ†’ Paid):** N/A - **Usage per user (avg gens/month):** N/A --- ## ๐Ÿ”ฎ Future Considerations (Not Currently Scheduled) ### Features (Post-PMF, after 50+ users) - Flow-based chained generation (complex workflows) - On-demand URL generation (programmatic HTML generation) - Namespaces / project organization - Team collaboration features (multi-user, agencies) - Advanced style presets / fine-tuning ### Market Expansion (After PMF with AI developers) - Agency tier ($149/mo for teams) - E-commerce vertical (product image generation, Shopify integration) - Enterprise tier (custom pricing, SLA, support) ### Operations (After $10K MRR) - Hire VA for customer support - Involve Ekaterina (wife) in admin/ops - Consider part-time dev help for non-core features - Explore partnership opportunities (integrations, resellers) --- ## ๐Ÿ“‹ Action Items Summary **This Week (Oct 30 - Nov 3):** 1. Create throwaway Reddit account 2. Post validation questions in r/ClaudeAI and r/ChatGPTCoding 3. Conduct 10 text-based interviews 4. Document results in validation scorecard 5. Make GO/PIVOT/STOP decision by Nov 3 **Next Week (Nov 4-10) - IF GO:** 1. Finalize MVP scope based on interview insights 2. Set up development environment (if not already done) 3. Begin MCP server implementation 4. Prepare beta access list **Next Week (Nov 4-10) - IF PIVOT:** 1. Select alternative ICP 2. Prepare new interview script 3. Begin second validation round --- ## ๐ŸŽฏ Success Definitions by Stage ### Pre-launch Success (Current) - โœ… ICP validated externally (60%+ interest, 40%+ willing to pay) - โœ… MVP scope locked (based on validated needs) - โœ… First 5 beta users identified from research ### Launch Success (Month 3-4) - โœ… 5-10 beta users actively using product - โœ… 50+ generations completed - โœ… 2+ credit purchases (willingness to pay confirmed) - โœ… No critical bugs blocking workflow ### Early Traction Success (Month 6) - โœ… $1-2K MRR - โœ… <5% monthly churn - โœ… Product-market fit signals ("can't live without") - โœ… Organic growth starting (word-of-mouth, referrals) ### Sustainability Success (Month 12) - โœ… $6K+ MRR (salary replacement level) - โœ… Predictable growth trajectory - โœ… Hybrid or full-time transition viable - โœ… Clear path to $10-15K MRR --- **Roadmap Owner:** @men + Oleg (joint ownership) **Last Review:** October 30, 2025 **Next Review:** November 4, 2025 (post-validation decision) **Version Control:** Track major changes via Git commits --- **Quick Reference Commands:** - Update metrics: Every Sunday evening - Review roadmap: After each decision gate - Update action items: As completed or priorities change - Archive completed sprints: Monthly cleanup