Banatie Project Roadmap
📅 Date Management Approach
Philosophy: Dates for completed work (track velocity), estimates for future work (reduce stress).
- ✅ Completed tasks: Record actual completion date
- 🔄 In progress: Show start date + estimated duration
- 📅 Future tasks: Show estimated duration only (e.g., "2-4 weeks", "3 months")
- 🎯 Milestones: Relative timeframes from key decision points (e.g., "Month 3 after validation")
Why: With 15-20 hrs/week availability, fixed deadlines create false pressure. Relative estimates allow flexibility while tracking actual velocity for better future planning.
🎯 Current Status
Phase: Pre-launch / ICP Validation Version: 1.1 Next Milestone: Complete ICP External Validation
✅ Completed Sprint: Foundation (Oct 20 - Oct 30)
✅ COMPLETED
- Market positioning clarified (Completed: Oct 25, 2025)
- ICP hypothesis validated internally - founder IS the ICP (Completed: Oct 28, 2025)
- Pricing strategy drafted - hybrid credits + subscription model (Completed: Oct 29, 2025)
- MVP scope defined - MCP + core features (Completed: Oct 30, 2025)
- Documentation framework established - filesystem MCP approach (Completed: Oct 30, 2025)
🔄 Active Sprint: ICP External Validation
Started: Oct 31, 2025 Est. duration: 2 weeks Owner: Oleg
Status
- Interviews completed: 0 / 10
- Decision: GO/PIVOT/STOP pending
Tasks
- Create throwaway Reddit account (stealth mode)
- Post in r/ClaudeAI: "How do you handle images in Claude Code?"
- Post in r/ChatGPTCoding: "AI-assisted devs: image generation workflow?"
- Conduct 10-15 text-based interviews via DM
- Fill validation scorecard after each interview
- Make GO/PIVOT/STOP decision based on results
⏸️ BLOCKED / WAITING
- MVP development (blocked by: need confirmed feature priorities from validation)
- Beta user outreach (blocked by: need validated messaging)
- Pricing finalization (blocked by: need ICP confirmation of willingness to pay)
📅 Upcoming Milestones
Post-Validation Phase (1-2 weeks after validation decision)
IF GO decision (60%+ willing to use, 40%+ willing to pay $20+):
- Finalize MVP scope based on validated top 3 needs from interviews
- Begin MCP server development
- Prepare beta access list from interviews (early adopters identified)
- Plan soft launch strategy (Reddit post schedule, messaging)
IF PIVOT decision (<60% interest OR weak willingness to pay):
- Select alternative ICP (agencies? e-commerce? different dev segment?)
- Prepare new interview script tailored to alternative ICP
- Run 5-10 more interviews (est. 1-2 weeks)
- Final GO/STOP decision
IF STOP decision (<40% interest, no one willing to pay):
- Document learnings (what didn't work, what insights gained)
- Thank all interviewees professionally
- Decide: tackle different problem OR shut down project
- Focus energy back on day job (reduce stress, reassess in 3-6 months)
MVP Development Phase (4-6 weeks)
(Assuming GO decision)
Est. duration: 4-6 weeks total
-
Weeks 1-2: Core generation pipeline + MCP integration
- REST API endpoints finalized
- Prompt Enhancement Agent working
- Image generation with @name references
- Basic storage + CDN integration
- Deliverable: Working API (generate + upload + references)
-
Week 3: MCP implementation
- MCP server setup (follow spec)
- Implement 3 tools: banatie_generate, banatie_upload, banatie_list_images
- Test with Claude Desktop
- Documentation for MCP usage
- Deliverable: Working MCP integration
-
Week 4: Transformations + UI refinement
- Image transformation service (Imageflow or Cloudflare)
- Refine demo UI (code snippets, transformation previews)
- Dashboard (history, usage stats)
- API key management
- Deliverable: Functional UI for testing
-
Week 5: Payments + polish
- Stripe integration (credit packs: $20, $50, $100)
- Free tier limits enforcement (10/month with watermark)
- Landing page copy + design
- API documentation (REST + MCP)
- Deliverable: Monetization-ready product
-
Week 6: Beta testing + iteration
- Invite 5-10 validated users from research
- High-touch onboarding (help with MCP setup)
- Gather feedback, fix critical bugs
- Iterate on UX pain points
- Deliverable: Product-market fit signals or pivot triggers
Soft Launch & Growth Phase (Months 3-6 after validation)
Month 3: First paying customers
- Goal: 5-10 beta users onboarded
- 50+ generations completed
- 2+ users purchase credits (willingness to pay validated)
- Target MRR: $200-500
Month 4: Soft launch to communities
- Post in r/ClaudeAI: "Show HN: Generate images from Claude Code via MCP"
- Indie Hackers build-in-public post
- Dev.to technical content (tutorial: "Automate image gen in Next.js with Claude Code")
- Target MRR: $500-1,000
Month 5: Growth optimization
- SEO content (start ranking for "AI image generation API", "Claude Code images")
- Community building (Discord, Reddit presence)
- Case studies from early users
- Target MRR: $1-2K (Side Project Validation milestone)
🎯 Long-term Goals (Relative Milestones)
Month 6 Checkpoint: Side Project Validation
Timeframe: ~6 months after validation Success criteria:
- MRR: $1-2K
- Customers: 10-20 paying
- Churn: <5% monthly
- Signal: Product-market fit OR clear pivot needed
Decision: Continue scaling OR reassess viability
Month 9 Checkpoint: Hybrid Mode Decision
Timeframe: ~9 months after validation Success criteria:
- MRR: $3-5K
- Customers: 30-50 paying
- Usage: Predictable growth pattern
Options:
- Negotiate 4-day work week with employer (80% salary = $4.8K)
- OR: Stay full-time job, continue nights/weekends
- Combined income: $7-10K/month (meets family needs + buffer)
Month 12 Checkpoint: Full-time Leap Evaluation
Timeframe: ~12 months after validation Success criteria:
- MRR: $6K+ (current salary replacement)
- OR: 12-month runway saved + high confidence in growth
- OR: MRR = $4-5K + spouse (Ekaterina) involved in admin with income
Decision: Go full-time on Banatie OR continue hybrid
Long-term vision (24-36 months from validation):
- $15-30K MRR: Sustainable solo/small team business
- Hire 1-2 people (support, marketing, or tech)
- Consider Ekaterina full-time on admin/ops
🚦 Decision Gates
GATE 1: ICP Validation (ACTIVE - Est. 2 weeks)
Started: Oct 31, 2025
Success criteria (ALL must be met):
- 60%+ interviews say "I would use this" (6 out of 10)
- 40%+ willing to pay $20+ (4 out of 10)
- 30%+ want early access (3 out of 10)
- KILLER USE CASE identified: ONE specific, frequent, expensive pain mentioned by 60%+ respondents (not scattered generic needs)
- Budget confirmed (they pay for other tools)
Possible outcomes:
- ✅ GO → Build MVP for AI developers (strong signals)
- 🔄 PIVOT → Test different ICP (weak signals, add 1-2 weeks)
- 🛑 STOP → Shut down or fundamental rethink (no market fit)
Review: Upon completion with @men
GATE 2: MVP Launch Readiness (Week 6 of MVP development)
Timeframe: ~6-8 weeks after Gate 1 GO decision
Success criteria:
- MCP integration works reliably (95%+ success rate)
- 5-10 beta users onboarded and generating images
- 50+ generations completed (usage validated)
- 2+ users purchase credits (monetization validated)
- No critical bugs blocking core workflow
Possible outcomes:
- ✅ LAUNCH → Soft launch to r/ClaudeAI, Indie Hackers
- 🔄 ITERATE → Add 1-2 weeks for bug fixes, UX improvements
- 🛑 PIVOT → Different approach needed (MCP too complex? Different features?)
Review: Upon completion
GATE 3: PMF Validation (Month 6 checkpoint)
Timeframe: ~6 months after Gate 1 GO decision
Success criteria:
- $1-2K MRR achieved
- <5% monthly churn (customers staying)
- "Can't live without" feedback from 3+ users
- Organic word-of-mouth starting (referrals, shares)
- Usage growing without marketing spend
Possible outcomes:
- ✅ SCALE → Invest in growth (content, partnerships, paid ads eventually)
- 🔄 OPTIMIZE → Refine product, improve conversion
- 🛑 PIVOT/STOP → No PMF achieved after 6 months, reassess fundamentally
Review: Upon reaching timeframe
⚠️ Risk Mitigation Watch
HIGH PRIORITY RISKS
1. Burnout Risk (Severity: HIGH)
- Factors: Full-time job + side project + newborn (Kirill, 2 weeks old) + family of 5
- Current exposure: Working 60+ hrs/week total (40 job + 20 Banatie)
- Monitor: Weekly health check-ins (Sundays)
- Mitigation:
- Strict time boundaries (no work after 10 PM)
- One full day off per week (family only)
- Use Agent Coding (Claude Code) to maximize efficiency
- Cut scope ruthlessly (MVP, not full vision)
- Red flags: Physical health decline, family tension, day job performance suffering
- Abort criteria: If health/family at risk, pause Banatie (not worth it)
2. Financial Pressure Risk (Severity: HIGH)
- Factors: Zero savings buffer, school tuition coming, single income ($6K/month)
- Current exposure: No emergency fund, Daniel's private school pending
- Monitor: Monthly expense tracking, runway calculation
- Mitigation:
- Keep day job until Banatie ≥ $6K MRR (non-negotiable)
- Negotiate hybrid work arrangement early (6-month mark if traction)
- Bootstrap (no fundraising until PMF clear)
- Minimize Banatie expenses (use family VPS, free tools)
- Red flags: Credit card debt accumulating, school tuition unpaid, family stress over money
- Abort criteria: If Banatie costs exceed $500/month without revenue
3. No PMF Risk (Severity: HIGHEST)
- Factors: Unvalidated ICP, new category (convergence play), complex product
- Current exposure: Hypothesis not yet tested with external users
- Monitor: Interview feedback, churn rate, usage metrics, qualitative signals
- Mitigation:
- Brutal ICP validation BEFORE building more (current sprint)
- Launch ultra-MVP (not full platform)
- 10-15 customer interviews BEFORE launch
- Set clear pivot triggers (see Phase 1 decision point)
- Red flags: No one willing to pay, high churn (>10%), "cool idea, but..." feedback
- Abort criteria: After 6 months, if <$500 MRR and no PMF signals → shut down
4. Employer Discovery Risk (Severity: MEDIUM)
- Factors: Building side project while employed, same industry (web dev, AI)
- Current exposure: Public presence needed for marketing (Twitter, LinkedIn, dev.to)
- Monitor: LinkedIn/social mentions, colleague conversations
- Mitigation strategies: (see
backlog/06-future-topics-backlog.md- "свечение фейса")- Use separate brand identity (Banatie, not personal)
- Delay LinkedIn posting until closer to launch
- Focus on dev.to, Indie Hackers (less employer monitoring)
- Check employment contract for IP clauses
- Red flags: Employer asks about side projects, colleagues mention seeing Banatie
- Abort criteria: If employer explicitly forbids, negotiate exit OR pause publicly
📊 Key Metrics Dashboard
Updated: Weekly (every Sunday evening)
Validation Metrics (Active Sprint)
Sprint started: Oct 31, 2025
- Interviews completed: 0 / 10
- Positive responses ("I would use"): - / -
- Willing to pay $20+: - / -
- Early access requests: - / -
Development Metrics (After GO decision)
- MVP features completed: - / 8
- Beta users onboarded: - / 10
- Generations completed: - / 50
- Credit purchases: - / 2
Business Metrics (Post-launch)
- MRR: $0
- Paying customers: 0
- Churn rate: N/A
- Conversion rate (Free → Paid): N/A
- Usage per user (avg gens/month): N/A
🔮 Future Considerations (Not Currently Scheduled)
Features (Post-PMF, after 50+ users)
- Flow-based chained generation (complex workflows)
- On-demand URL generation (programmatic HTML generation)
- Namespaces / project organization
- Team collaboration features (multi-user, agencies)
- Advanced style presets / fine-tuning
Market Expansion (After PMF with AI developers)
- Agency tier ($149/mo for teams)
- E-commerce vertical (product image generation, Shopify integration)
- Enterprise tier (custom pricing, SLA, support)
Operations (After $10K MRR)
- Hire VA for customer support
- Involve Ekaterina (wife) in admin/ops
- Consider part-time dev help for non-core features
- Explore partnership opportunities (integrations, resellers)
📋 Action Items Summary
Active Sprint (ICP Validation - Started Oct 31):
- Create throwaway Reddit account
- Post validation questions in r/ClaudeAI and r/ChatGPTCoding
- Conduct 10 text-based interviews
- Document results in validation scorecard
- Make GO/PIVOT/STOP decision
After Validation - IF GO:
- Finalize MVP scope based on interview insights
- Set up development environment (if not already done)
- Begin MCP server implementation
- Prepare beta access list
After Validation - IF PIVOT:
- Select alternative ICP
- Prepare new interview script
- Begin second validation round (est. 1-2 weeks)
🎯 Success Definitions by Stage
Pre-launch Success (Current)
- ✅ ICP validated externally (60%+ interest, 40%+ willing to pay)
- ✅ MVP scope locked (based on validated needs)
- ✅ First 5 beta users identified from research
Launch Success (Month 3-4)
- ✅ 5-10 beta users actively using product
- ✅ 50+ generations completed
- ✅ 2+ credit purchases (willingness to pay confirmed)
- ✅ No critical bugs blocking workflow
Early Traction Success (Month 6)
- ✅ $1-2K MRR
- ✅ <5% monthly churn
- ✅ Product-market fit signals ("can't live without")
- ✅ Organic growth starting (word-of-mouth, referrals)
Sustainability Success (Month 12)
- ✅ $6K+ MRR (salary replacement level)
- ✅ Predictable growth trajectory
- ✅ Hybrid or full-time transition viable
- ✅ Clear path to $10-15K MRR
Roadmap Owner: @men + Oleg (joint ownership) Last Updated: October 31, 2025 Next Review: Upon completion of ICP validation Version Control: Track major changes via Git commits
Quick Reference Commands:
- Update metrics: Every Sunday evening
- Review roadmap: After each decision gate
- Update action items: As completed or priorities change
- Archive completed sprints: When moving to next phase
- Mark tasks complete: Record actual completion dates for velocity tracking